Select By Site Code

For Site Code TRA-34

CREATION
DATE
AUTHOR TITLE DOCUMENT
NUMBER
REV
08-AUG-16 NOT SPECIFIED EXPLANATION OF SIGNIFICANT DIFFERENCES, RESULTING FROM THE 2010 TO 2014 FIVE-YEAR REVIEW, TO IMPLEMENT CHANGES IN RECORDS OF DECISION AT THE IDAHO NATIONAL LABORATORY SITE DOE/ID-11548 0
01-SEP-11 NOT SPECIFIED EXPLANATION OF SIGNIFICANT DIFFERENCES TO REVISE INSTITUTIONAL CONTROLS IN VARIOUS RECORDS OF DECISION AT THE IDAHO NATIONAL LABORATORY SITE DOE/ID-11439 0
27-FEB-07 JOLLEY, W. L. FIVE (5) YEAR REVIEW OF COMPREHENSIVE ENVIRONMENTAL RESPONSE COMPENSATION, AND LIABILITY ACT (CERCLA) RESPONSE ACTIONS AT THE IDAHO NATIONAL LABORATORY (INL) DOE/NE-ID-11201 03
04-DEC-06 OPALSKI, D. D. ENVIRONMENTAL PROTECTION AGENCY (EPA) CONCURRENCE WITH THE IDAHO NATIONAL LABORATORY (INL) FIVE (5) YEAR REVIEW, 2006 25063 00
16-AUG-06 JOLLEY, W. L. IDAHO NATIONAL LABORATORY (INL) SITE WIDE INSTITUTIONAL CONTROLS ANNUAL REPORT - FY 2006 (FY-06) DOE/ID-11289 00
16-JUN-06 JOLLEY, W. L. FIVE (5) YEAR REVIEW OF CERCLA RESPONSE ACTIONS AT THE IDAHO NATIONAL LABORATORY (INL) DOE/NE-ID-11201 01
04-OCT-05 JOLLEY, W. L. FIVE YEAR REVIEW OF CERCLA RESPONSE ACTIONS AT THE IDAHO NATIONAL LABORATORY (INL) DOE/NE-ID-11201 00
23-SEP-05 FITCH, D. R. IDAHO NATIONAL LABORATORY (INL) SITE WIDE INSTITUTIONAL CONTROLS ANNUAL REPORT - FY 2005 (FY-05) DOE/ID-11250 00
30-JUL-03 JOLLEY, W. L. FY-2003 (FY-03) ANNUAL INSTITUTIONAL CONTROLS ASSESSMENT REPORT FOR TEST REACTOR AREA (TRA) OPERABLE UNIT (OU) 2-13 DOE/ID-11108 00
16-APR-03 NELSON, G. E. INEEL WASTE AREA GROUP 2 (WAG-2) - AGREEMENTS CONCERNING FINALIZING THE WAG-2 FIVE YEAR REMEDY REVIEW, TEST REACTOR AREA (TRA) OPERABLE UNIT (OU) 2-13 EM-ER-03-103 00
21-NOV-02 JAMES, R. E. FY-2002 (FY-02) ANNUAL INSTITUTIONAL CONTROLS INSPECTION REPORT FOR THE TEST REACTOR AREA (TRA), OPERABLE UNITS (OU) 2-13 AND 2-14 (FINAL) INEEL/EXT-02-00933 00
04-NOV-02 NELSON, G. E. TRANSMITTAL OF FY-2002 (FY-02) ANNUAL INSTITUTIONAL CONTROLS INSPECTION REPORT FOR THE TEST REACTOR AREA (TRA), OPERABLE UNITS (OU) 2-13 AND 2-14 (FINAL) EM-ER-02-187 00
08-APR-02 MCGUIRE, M. J. FISCAL YEAR 2001 (FY-2001) INSTITUTIONAL CONTROL INSPECTION REPORT FOR THE TEST REACTOR AREA (TRA), OPERABLE UNIT (OU) 2-13 INEEL/EXT-01-00772 00
26-FEB-01 SEELEY, V. T. INSTITUTIONAL CONTROLS ANNUAL MONITORING REPORT FOR TEST REACTOR AREA (TRA) OPERABLE UNIT (OU) 2-13 INEEL/EXT-2000-01413 00
26-JUN-00 AR COORDINATOR OPERABLE UNIT (OU) 2-13 - IDAHO NATIONAL ENGINEERING AND ENVIRONMENTAL LABORATORY (INEEL) ADMINISTRATIVE RECORD (AR) INDEX FOR THE TEST REACTOR AREA (TRA) PERCHED WATER SYSTEM REMEDIAL INVESTIGATION FEASIBILITY STUDY (RI/FS) OU 2-13 AR.INDEX.OU.2-13 00
17-MAY-00 SHERWOOD, J. A. EXPLANATION OF SIGNIFICANT DIFFERENCES (ESD) TO THE RECORD OF DECISION (ROD) FOR TEST REACTOR AREA (TRA) OPERABLE UNIT (OU) 2-13 DOE/ID-10744 00
10-MAR-00 WIGGINS, D. J. OPERATIONS AND MAINTENANCE (O&M) PLAN FOR FINAL SELECTED REMEDIES & INSTITUTIONAL CONTROLS AT TEST REACTOR AREA (TRA) OPERABLE UNIT (OU) 2-13 DOE/ID-10658 03
21-DEC-99 AR COORDINATOR OPERABLE UNIT (OU) 10-06 - IDAHO NATIONAL ENGINEERING AND ENVIRONMENTAL LABORATORY (INEEL) ADMINISTRATIVE RECORD (AR) INDEX FOR RADIONUCLIDE CONTAMINATED SOILS REMEDIAL INVESTIGATION FEASIBILITY STUDY (RI/FS) AR.INDEX.OU.10-06 00
01-AUG-99 INEEL COMMUNITY RELATIONS INEEL COMMUNITY RELATIONS PLAN KICKOFF FACT SHEET - COMPREHENSIVE INVESTIGATION UNDER WAY FOR WASTE AREA GROUP 10 (WAG-10) 18049 00
14-OCT-97 AR COORDINATOR OPERABLE UNIT (OU) 2-04 - IDAHO NATIONAL ENGINEERING AND ENVIRONMENTAL LABORATORY (INEEL) ADMINISTRATIVE RECORD (AR) INDEX FOR THE TRACK 2 INVESTIGATION OF TEST REACTOR AREA (TRA) OU 2-04 AR.INDEX.OU.2-04 00
07-FEB-97 JENSEN, N. R. TRANSMITTAL FINAL REMEDIAL INVESTIGATION FEASIBILITY STUDY (RI/FS) REPORT FOR WASTE AREA GROUP 2 (WAG-2) COMPREHENSIVE REMEDIAL INVESTIGATION FEASIBILITY STUDY, OPERABLE UNIT (OU) 2-13 AT THE IDAHO NATIONAL ENGINEERING LABORATORY (INEL) OPE-ER-11-97 00
03-FEB-97 JENSEN, N. R. TRANSMITTAL OF FINAL REMEDIAL INVESTIGATION FEASIBILITY STUDY (RI/FS) REPORT FOR WASTE AREA GROUP 2 (WAG-2) COMPREHENSIVE REMEDIAL INVESTIGATION FEASIBILITY STUDY, OPERABLE UNIT (OU) 2-13 AT THE IDAHO NATIONAL ENGINEERING LABORATORY (INEL) OPE-ER-10-97 00
01-FEB-97 BURNS, D. E. COMPREHENSIVE REMEDIAL INVESTIGATION FEASIBILITY STUDY (RI/FS) FOR TEST REACTOR AREA (TRA) OPERABLE UNIT (OU) 2-13 AT THE IDAHO NATIONAL ENGINEERING & ENVIRONMENTAL LABORATORY (INEEL) DOE/ID-10531 00
02-DEC-96 COTTEN, G. B. SUMMARY REPORT FOR OPERABLE UNIT (OU) 10-06 RADIONUCLIDE CONTAMINATED SOILS REMOVAL 10562 00
01-JUL-96 FITCH, D. R. HEALTH & SAFETY PLAN (HSP) FOR RADIONUCLIDE CONTAMINATED SOILS REMOVAL ACTION OPERABLE UNIT (OU) 10-06 INEL-95/0347 01
19-OCT-95 GREEN, L. A. DOE RESPONSE TO ENVIRONMENTAL PROTECTION AGENCY (EPA) COMMENTS ON DRAFT FINAL SUMMARY REPORT FOR WASTE AREA GROUP 3 (WAG-3) & WASTE AREA GROUP 10 (WAG-10) RADIONUCLIDE CONTAMINATED SOILS TREATABILITY STUDY (TS) 10445 00
19-OCT-95 GREEN, L. A. TRANSMITTAL OF DRAFT FINAL SUMMARY REPORT FOR WASTE AREA GROUP 3 (WAG-3) & WASTE AREA GROUP 10 (WAG-10) RADIONUCLIDE CONTAMINATED SOILS TREATABILITY STUDY (TS) & DOE RESPONSE TO ENVIRONMENTAL PROTECTION AGENCY ( EPA) COMMENTS OPE-ER-201-95 00
10-OCT-95 JORGENSEN, D. K. CHANGE IN TITLE & NAME OF DRAFT OU 10-06 REMEDIAL INVESTIGATION FEASIBILITY STUDY (RI/FS) FOR PLACEMENT INTO ADMINISTRATIVE RECORD (AR) DKJ-13-95 00
01-OCT-95 GREENWELL, R. D. DRAFT FINAL SUMMARY REPORT FOR WASTE AREA GROUP 3 (WAG-3) & WASTE AREA GROUP 10 (WAG-10) RADIONUCLIDE CONTAMINATED SOILS TREATABILITY STUDY (TS) INEL-94/0171 00
01-AUG-95 DOE DOE-ID LEAD AGENCY ACTION MEMORANDUM FOR THE NON TIME CRITICAL REMOVAL ACTION (NTCRA) AT OU 10-06 RADIONUCLIDE CONTAMINATED SOIL LOCATIONS AT THE INEL 10043 00
01-AUG-95 PARSONS CORPORATION HEALTH AND SAFETY PLAN (HSP) FOR RADIONUCLIDE CONTAMINATED SOILS REMOVAL ACTION OU 10-06 (PARSONS #ES-21.6.12) INEL-95/0347 00
01-AUG-95 PARSONS CORPORATION FIELD SAMPLING PLAN (FSP) FOR RADIONUCLIDE CONTAMINATED SOILS REMOVAL ACTION OU 10-06 (PARSONS #ES-21.6.3) INEL-95/0365 00
01-AUG-95 GREEN, L. A. TRANSMITTAL OF FINAL ACTION MEMORANDUM FOR OU 10-06 REMOVAL ACTION AT THE INEL OPE-ER-95-144 00
28-JUL-95 PARSONS CORPORATION ENVIRONMENTAL RESTORATION (ER) REMOVAL ACTION WORK PLAN FOR RADIONUCLIDE CONTAMINATED SOILS AT OU 10-06 INEL-95/0326 02
05-JUL-95 SATTGAST, L. PUBLIC COMMENT AND RESPONSE ON OPERABLE UNIT (OU) 10-06 RADIONUCLIDE CONTAMINATED SOILS REMOVAL ACTION 10046 00
05-JUL-95 KOCH, D. F. IDHW REVIEW COMMENTS OF BASELINE RISK ASSESSMENT (BRA) OF DRAFT RI/FS FOR OU 10-06 RADIONUCLIDE CONTAMINATED SOILS AT INEL 10051 00
19-JUN-95 JONES, E. EPA REVIEW COMMENTS OF RADIONUCLIDE CONTAMINATED SOILS OU 10-06 DRAFT REMEDIAL INVESTIGATION FEASIBILITY STUDY (RI/FS) 10050 00
15-JUN-95 BURNS, S. M. OPERABLE UNIT (OU) 10-06 NON TIME CRITICAL REMOVAL ACTION (NTCRA) ENGINEERING EVALUATION COST ANALYSIS (EE/CA) APPROVAL MEMORANDUM 10021 00
10-JUN-95 MARTY, R. C. ENGINEERING EVALUATION COST ANALYSIS (EE/CA) FOR OPERABLE UNIT (OU) 10-06 RADIONUCLIDE CONTAMINATED SOILS REMOVAL ACTION AT INEL, VOLUME III (VOL.03) INEL-95/0259,VOL.03 00
08-JUN-95 ROOD, S. M. ENGINEERING EVALUATION COST ANALYSIS (EE/CA) FOR OPERABLE UNIT (OU) 10-06 RADIONUCLIDE CONTAMINATED SOILS REMOVAL ACTION AT INEL, VOLUME I, (VOL.01) INEL-95/0259,VOL.01 00
08-JUN-95 ROOD, S. M. ENGINEERING EVALUATION COST ANALYSIS (EE/CA) FOR OPERABLE UNIT (OU) 10-06 RADIONUCLIDE CONTAMINATION SOILS REMOVAL ACTION AT (INEL), VOLUME II, (VOL.02) INEL-95/0259,VOL.02 00
04-MAY-95 DOE, EPA, IDHW ACTION DETERMINATION FOR WAG-10 OU 10-06 RADIONUCLIDE CONTAMINATED SOIL SITES 10016 00
19-JAN-95 DOE, EPA, IDHW TRACK 2 DECISION STATEMENT FOR OU 2-04 TRACK 2 SUMMARY REPORT FOR TRA - TRA-653, TRA-626, TRA-619, PW-13, TRA-09, TRA-670, & TRA-627 - NO FURTHER ACTION DETERMINATION 5861 00
04-NOV-94 KOCH, D. F. IDHW-DEQ RECOMMENDATIONS FOR OU 2-04 TRACK 2 SUMMARY REPORT 5790 00
11-OCT-94 MEYER, L. EPA RECOMMENDATIONS ON THE TRACK 2 SUMMARY REPORT FOR WASTE AREA GROUP 2 (WAG-2) OPERABLE UNIT (OU) 2-04 5513 00
01-MAY-94 EG&G IDAHO, INC. TECHNICAL MEMORANDUM BASELINE RISK ASSESSMENT (BRA) FOR OU 10-06 RADIONUCLIDE CONTAMINATED SOILS RI/FS DRAFT EGG-ER-11316 00
07-APR-94 LYLE, J. L. TRANSMITTAL OF THE DOCUMENT REVISION REQUEST (DRR) FOR OPERABLE UNIT (OU) 10-06 PHASE II SAMPLING & ANALYSIS PLAN (SAP) & HEALTH & SAFETY PLAN (HSP) OPE-ER-085-94 00
01-APR-94 LYLE, J. L. TRANSMITTAL OF THE REVISED TRACK 2 SUMMARY REPORT FOR OPERABLE UNIT (OU) 2-04 AND THE DOE-ID TRACK 2 DECISION STATEMENT OPE-ER-78-94 00
01-MAR-94 SHERWOOD, J. A. PRELIMINARY SCOPING TRACK 2 SUMMARY REPORT FOR THE TRA OU 2-04: FUEL SPILLS EGG-ER-11110 02
01-MAR-94 HANEY, T. J. HEALTH & SAFETY PLAN (HSP) FOR PHASE II OF THE OPERABLE UNIT (OU) 10-06 RADIONUCLIDE CONTAMINATED SOILS REMEDIAL INVESTIGATION FEASIBILITY STUDY (RI/FS) EGG-ER-11231 01
07-FEB-94 LYLE, J. L. TRANSMITTAL OF THE PHASE II SAMPLING & ANALYSIS PLAN (SAP) FOR THE RADIONUCLIDE CONTAMINATED SOILS REMEDIAL INVESTIGATION FEASIBILITY STUDY (RI/FS) OU 10-06 OPE-ER-030-94 00
01-JAN-94 HANEY, D. F. SAMPLING & ANALYSIS PLAN (SAP) FOR PHASE II OF OU 10-06 RADIONUCLIDE CONTAMINATED SOILS REMEDIAL INVESTIGATION FEASIBILITY STUDY (RI/FS) EGG-ER-10971 00
01-DEC-93 MSE, INC. FINAL SCOPE OF WORK FOR OU 10-06 RADIONUCLIDE CONTAMINATED SOILS REMEDIAL INVESTIGATION FEASIBILITY STUDY (RI/FS) EGG-ER-10902 00
08-JUL-87 ALEXANDER, T. G. INITIAL ASSESSMENT - TRA-34 NORTH STORAGE AREA 2844 00


Send Questions and Comments to: RecordsManagement@icp.doe.gov

Previous Page | Administrative Record Home Page