Select By Operable Unit (OU)

For Operable Unit 3/GEN

CREATION
DATE
AUTHOR TITLE DOCUMENT
NUMBER
REV
06-AUG-18 NOT SPECIFIED INL SITE-WIDE INSTITUTIONAL CONTROLS, AND OPERATIONS AND MAINTENANCE ANNUAL REPORT - FY2017 RPT-1635 0
18-DEC-17 NOT SPECIFIED INL SITE-WIDE INSTITUTIONAL CONTROLS, AND OPERATIONS AND MAINTENANCE PLAN FOR CERCLA RESPONSE ACTIONS DOE/ID-11042 10
01-MAY-17 NOT SPECIFIED INL SITE-WIDE INSTITUTIONAL CONTROLS, AND OPERATIONS AND MAINTENANCE ANNUAL REPORT - FY2016 RPT-1543 0
26-JAN-17 KOCH, DARYL F. DEQ CONCURRENCE TO ADDENDUM TO TABLES 1 AND 3 OF THE GENERAL ACTION MEMO FOR GENERAL DECOMMISSIONING ACTIVITIES UNDER THE IDAHO CLEANUP PROJECT (DOE/ID-11293, REVISION 3) (EM-FMDP-17-001) 5661786 0
26-JAN-17 FAULK, DENNIS EPA CONCURRENCE TO ADDENDUM TO TABLES 1 AND 3 OF THE GENERAL ACTION MEMO FOR GENERAL DECOMMISSIONING ACTIVITIES UNDER THE IDAHO CLEANUP PROJECT (DOE/ID-11293, REVISION 3) (EM-FMDP-17-001) 5661787 0
18-JAN-17 WHITHAM, KENNETH ADDENDUM TO TABLES 1 AND 3 OF THE GENERAL ACTION MEMO FOR GENERAL DECOMMISSIONING ACTIVITIES UNDER THE IDAHO CLEANUP PROJECT (DOE/ID-11293, REVISION 3) (EM-FMDP-17-001) EM-FMDP-17-001 0
01-JAN-17 NOT SPECIFIED INL SITE-WIDE INSTITUTIONAL CONTROLS, AND OPERATIONS AND MAINTENANCE ANNUAL REPORT - FY 2015 RPT-1503 0
01-JUN-16 NOT SPECIFIED QUALITY ASSURANCE PROJECT PLAN FOR WASTE AREA GROUPS 1, 2, 3, 4, 5, 6, 7, 9, 10, AND REMOVAL ACTIONS DOE/ID-10587 11
08-FEB-16 FAULK, DENNIS EPA CONCURRENCE ON THE IDAHO NATIONAL LAB 5 YEAR REVIEW 5282268 0
31-DEC-15 NOT SPECIFIED FIVE-YEAR REVIEW OF CERCLA RESPONSE ACTIONS AT THE IDAHO NATIONAL LABORATORY SITE - FISCAL YEARS 2010-2014 DOE/ID-11513 0
01-AUG-15 NOT SPECIFIED INL SITE COMMUNITY INVOLVEMENT PLAN DOE/ID-11518 0
01-JUN-15 NOT SPECIFIED ACTION MEMORANDUM FOR GENERAL DECOMMISSIONING ACTIVITIES UNDER THE IDAHO CLEANUP PROJECT DOE/ID-11293 3
01-MAY-15 NOT SPECIFIED INL SITE-WIDE INSTITUTIONAL CONTROLS, AND OPERATIONS AND MAINTENANCE ANNUAL REPORT - FY 2014 RPT-1361 0
01-APR-15 NOT SPECIFIED ACTION MEMORANDUM FOR GENERAL DECOMMISSIONING ACTIVITIES UNDER THE IDAHO CLEANUP PROJECT DOE/ID-11293 2
01-MAY-14 NOT SPECIFIED INL SITE-WIDE INSTITUTIONAL CONTROLS, AND OPERATIONS AND MAINTENANCE ANNUAL REPORT - FY 2013 RPT-1268 0
01-SEP-13 NOT SPECIFIED INL SITE-WIDE INSTITUTIONAL CONTROLS, AND OPERATIONS AND MAINTENANCE PLAN FOR CERCLA RESPONSE ACTIONS DOE/ID-11042 8
01-JUN-13 NOT SPECIFIED INL SITE-WIDE INSTITUTIONAL CONTROLS, AND OPERATIONS AND MAINTENANCE ANNUAL REPORT - FY 2012 RPT-1196 0
01-JUL-12 NOT SPECIFIED INL SITE-WIDE INSTITUTIONAL CONTROLS, AND OPERATIONS AND MAINTENANCE ANNUAL REPORT - FY 2011 RPT-1001 0
30-APR-12 NOT SPECIFIED INL SITE-WIDE INSTITUTIONAL CONTROLS, AND OPERATIONS AND MAINTENANCE PLAN FOR CERCLA RESPONSE ACTIONS DOE/ID-11042 7
16-APR-12 FAULK, DENNIS EPA CONCURRENCE - ADDITION OF BUILDINGS TO THE ACTION MEMORANDUM FOR GENERAL DECOMMISSIONING ACTIVITIES 3956551 0
09-APR-12 KOCH, DARYL F. DEQ CONCURRENCE - REQUEST FOR ADDENDUM TO TABLE 1 OF THE ACTION MEMORANDUM FOR GENERAL DECOMMISSIONING ACTIVITIES UNDER THE IDAHO CLEANUP PROJECT (DOE/ID-11293, REVISION 1) 3956550 0
09-APR-12 SHAW, R. MARK ADDENDUM TO TABLE 1. OF THE ACTION MEMORANDUM FOR GENERAL DECOMMISSIONING ACTIVITIES UNDER THE IDAHO CLEANUP PROJECT (DOE/ID-11293, REVISION 1) (EM-FMDP-12-027) EM-FMDP-12-027 0
03-JAN-12 BULLOCK, ROBERT E. CONCURRENCE ON LEAVING PIPING WITH LEADED JOINTS BENEATH CPP-601 AND CPP-602 AS IMPRACTICAL TO REMOVE AT THE INTEC CPP-601/627/640 LANDFILL CLOSURE ON THE INL (EPA ID NO. IDD4890008952) IR-25316 0
07-FEB-11 OPALSKI, DANIEL D. U. S. ENVIRONMENTAL PROTECTION AGENCY (EPA) CONCURRENCE ON THE FIVE-YEAR REVIEW FOR IDAHO NATIONAL LABORATORY FISCAL YEARS 2005-2009 4544925 0
19-JAN-11 NOT SPECIFIED FIVE-YEAR REVIEW OF CERCLA RESPONSE ACTIONS AT THE IDAHO NATIONAL LABORATORY SITE - FISCAL YEARS 2005-2009 (PART 1) DOE/ID-11429 (PART 1) 0
19-JAN-11 NOT SPECIFIED FIVE-YEAR REVIEW OF CERCLA RESPONSE ACTIONS AT THE IDAHO NATIONAL LABORATORY SITE - FISCAL YEARS 2005-2009 (PART 2) DOE/ID-11429 (PART 2) 0
13-JAN-11 NOT SPECIFIED INL SITE-WIDE INSTITUTIONAL CONTROLS AND OPERATIONS AND MAINTENANCE ANNUAL REPORT - FY 2010 RPT-759 0
31-AUG-09 THOMPSON, R. G. QUALITY ASSURANCE PROJECT PLAN FOR WASTE AREA GROUPS 1, 2, 3, 4, 5, 6, 7, 10, AND REMOVAL ACTIONS DOE/ID-10587 10
25-JUN-09 NOT SPECIFIED ICDF COMPLEX WASTE ACCEPTANCE CRITERIA DOE/ID-10881 7
19-FEB-09 NOT SPECIFIED ICDF COMPLEX WASTE ACCEPTANCE CRITERIA DOE/ID-10881 6
09-JAN-09 RENO, SCOTT L. ACTION MEMORANDUM FOR GENERAL DECOMMISSIONING ACTIVITIES UNDER THE IDAHO CLEANUP PROJECT (ICP) DOE/ID-11293 1
11-AUG-08 EATON, D. L. ACTION MEMORANDUM FOR DECOMMISSIONING CPP-601/640 FUEL REPROCESSING FACILITIES DOE/ID-11360 0
08-JUL-08 CAHN, L. S. ICDF DETECTION MONITORING BIENNIAL REPORT (2006-2007) DOE/ID-11373 0
05-JUN-08 NOT SPECIFIED ICDF COMPLEX WASTE ACCEPTANCE CRITERIA DOE/ID-10661 5
23-APR-08 NOT SPECIFIED TITLE TEST-1 04
05-FEB-08 JOLLEY, W. L. IDAHO NATIONAL LABORATORY (INL) SITEWIDE INSTITUTIONAL CONTROLS, AND OPERATIONS AND MAINTENANCE (O&M) PLAN FOR COMPREHENSIVE ENVIRONMENTAL RESPONSE, COMPENSATION, AND LIABILITY ACT (CERCLA) RESPONSE ACTIONS DOE/ID-11042 04
14-JAN-08 EATON, D. L. ENGINEERING EVALUATION/COST ANALYSIS (EE/CA) FOR DECOMMISSIONING OF THE CHEMICAL PROCESSING PLANT (CPP-601/640) FUEL REPROCESSING FACILITIES DOE/ID-11346 02
22-MAY-07 MCMANAMON, L. E. ENVIRONMENTAL RESTORATION PROJECT HEALTH AND SAFETY PLAN (HSP OR HASP) PLN-2128 03
04-JAN-07 CROSON, D. V. FINAL REMOVAL ACTION REPORT FOR THE CPP-603A BASIN FACILITY DOE/ID-11306 01
15-DEC-06 CROSON, D. V. FINAL REMOVAL ACTION REPORT FOR THE CPP-603A BASIN FACILITY DOE/ID-11306 00
31-OCT-06 MCMANAMON, L. E. MISCELLANEOUS SITES CLEANUP PROJECT (MSCP) HEALTH AND SAFETY PLAN (HSP OR HASP) PLN-2128 02
06-SEP-06 ROUSSEAU, J. P. RESPONSE TO COMMENTS ALLEGING IDAHO NATIONAL LABORATORY (INL) RELATED CS-137 AND SR-90 CONTAMINATION IN THE MICHAUD FLATS AREA NEAR POCATELLO, IDAHO CCN 304024 00
27-JUL-06 JOLLEY, W. L. IDAHO NATIONAL LABORATORY (INL) SITEWIDE INSTITUTIONAL CONTROLS PLAN DOE/ID-11042 03
13-JUL-06 MCMANAMON, L. E. MISCELLANEOUS SITES CLEANUP PROJECT (MSCP) HEALTH AND SAFETY PLAN (HSP OR HASP) PLN-2128 01
05-JUN-06 RICHARDS, B. T. REMOVAL ACTION WORK PLAN (RAWP) FOR THE CHEMICAL PROCESSING PLANT (CPP-603A) BASIN FACILITY DOE/NE-ID-11214 02
31-MAY-06 MCMANAMON, L. E. MISCELLANEOUS SITES CLEANUP PROJECT (MSCP) HEALTH AND SAFETY PLAN (HSP OR HASP) PLN-2128 00
08-MAR-06 PROVENCHER, R. B. APPROVAL TO PROCEED WITH THE PREPARATION OF AN ENGINEERING EVALUATION/COST ANALYSIS (EE/CA) FOR THE FINAL DECOMMISSIONING OF THE CHEMICAL PROCESSING PLANT 601 (CPP-601) FUEL REPROCESSING COMPLEX AT THE IDAHO NATIONAL LABORATORY (INL) SITE FMDP-RFDP-06-028 00
07-FEB-06 COLE, M. R. FINAL REPORT FOR THE DECONTAMINATION AND DECOMMISSIONING (D&D) OF CPP-627 REMOTE ANALYTICAL FACILITY ICP/EXT-06-01145 00
22-SEP-05 FITCH, D. R. IDAHO NATIONAL LABORATORY (INL) SITE WIDE OPERATIONS AND MAINTENANCE (O&M) REPORT FOR CERCLA RESPONSE ACTIONS - FY 2005 (FY-05) DOE/ID-11249 00
30-AUG-05 FITCH, D. R. IDAHO NATIONAL LABORATORY (INL) SITE WIDE OPERATIONS AND MAINTENANCE (O&M) REPORT FOR CERCLA RESPONSE ACTIONS - FY 2004 (FY-04) DOE/NE-ID-11200 00
29-JUN-05 MACCONNEL, M. J. SUBMITTAL OF ADDITIONAL INFORMATION AND REQUEST FOR APPROVAL OF PERMANENT ABANDONMENT FOR CLASS V SHALLOW INJECTION WELLS MAH-CA-CT-319, 40-CPP, 45-CPP, AND 46-CPP 34886 00
01-JUN-05 LEWIS, M. G. ADDITIONAL INFORMATION FOR SHALLOW INJECTION WELLS MAH-CA-CT-319, 40-CPP, 45-CPP, AND 46-CPP ICP/EXT-05-00934 00
15-FEB-05 RICHARDS, B. T. REMOVAL ACTION WORK PLAN FOR THE CPP-603 BASIN FACILITY DOE/NE-ID-11214 00
06-JAN-05 RICHARDS, B. T. ACTION MEMORANDUM FOR THE NON TIME CRITICAL REMOVAL ACTION (NTCRA) AT THE CPP-603A BASINS, IDAHO NUCLEAR TECHNOLOGY AND ENGINEERING CENTER (INTEC) DOE/NE-ID-11194 00
07-DEC-04 AR COORDINATOR CPP-603 REMOVAL ACTION - IDAHO COMPLETION PROJECT (ICP) ADMINISTRATIVE RECORD (AR) INDEX FOR THE NON TIME CRITICAL REMOVAL ACTION (NTCRA) AT THE IDAHO NATIONAL ENGINEERING AND ENVIRONMENTAL LABORATORY (NEEL) FUEL STORAGE BASIN COMPLEX AT CPP-630 AR.INDEX.NTCRA.CPP-603 00
31-AUG-04 ICP COMMUNITY RELATIONS AGENCIES EXTEND COMMENT PERIOD ON PLAN TO REMOVE WATER FROM OLD INEEL SPENT FUEL BASINS 24883 00
26-AUG-04 RICHARDS, B. T. ENGINEERING EVALUATION COST ANALYSIS (EE/CA) FOR THE CPP-603A BASIN NON TIME CRITICAL REMOVAL ACTION (NTCRA) IDAHO NUCLEAR TECHNOLOGY AND ENGINEERING CENTER (INTEC) DOE/NE-ID-11140 01
04-AUG-04 DOE NOTICE OF AVAILABILITY - AGENCIES PROPOSE REMOVING WATER FROM OLD INEEL SPENT FUEL BASIN TO REMOVE POTENTIAL RISK TO AQUIFER 24878 00
02-AUG-04 HAIN, K. E. DOE APPROVAL OF REQUEST FOR EXTENSION OF THE PUBLIC COMMENT PERIOD FOR THE CPP-603A BASIN ENGINEERING EVALUATION COST ANALYSIS (EE/CA) EM-ER-04-166 00
02-AUG-04 HAIN, K. E. TRANSMITTAL OF THE ENGINEERING EVALUATION COST ANALYSIS (EE/CA) FOR THE CPP-603A BASIN NON TIME CRITICAL REMOVAL ACTION (NTCRA), IDAHO NUCLEAR TECHNOLOGY AND ENGINEERING CENTER (INTEC), DOE/NE-ID-11140, JULY 2004 (07/04) EM-ER-04-171 00
22-JUL-04 CLOUGH, M. K. DEPARTMENT OF ENVIRONMENTAL QUALITY (DEQ) RESPONSE TO DRAFT CPP-603A BASIN NON TIME CRITICAL REMOVAL ACTION (NTCRA) ENGINEERING EVALUATION COST ANALYSIS (EE/CA), IDAHO NUCLEAR TECHNOLOGY AND ENGINEERING CENTER (INTEC) 24876 00
22-JUL-04 CLOUGH, M. K. IDAHO DEPARTMENT OF ENVIRONMENTAL QUALITY (DEQ) REVIEW OF THE ENGINEERING EVALUATION COST ANALYSIS (EE/CA) FOR THE CPP-603A NON TIME CRITICAL REMOVAL ACTION (NTCRA), DRAFT DOCUMENT (DOE/NE-ID-11140) 24877 00
21-JUN-04 KOCH, D. F. DEPARTMENT OF ENVIRONMENTAL QUALITY (DEQ) CONCURRENCE ON A SUITABILITY DETERMINATION FOR AN OFF-SITE FACILITY TO MANAGE WASTE AREA GROUP 3 (WAG-3) WASTE 24870 00
21-JUN-04 MCCARTHY, J. M. ENGINEERING DESIGN FILE (EDF) - STREAMLINED RISK ASSESSMENT FOR CPP-603 ENGINEERING EVALUATION COST ANALYSIS (EE/CA) EDF-4488 01
18-JUN-04 HAIN, K. E. TRANSMITTAL OF REMOVAL ACTION WORK PLAN, ACTION MEMORANDUM, AND WASTE MANAGEMENT PLAN (WMP) FOR THE DECONTAMINATION AND DECOMMISSIONING (D&D) OF BUILDING CPP-627, THE REMOTE ANALYTICAL FACILITY EM-ER-04-125 00
17-JUN-04 MCCARTHY, J. M. ENGINEERING DESIGN FILE (EDF) - SOIL CONTAMINATION GROUNDWATER PATHWAY RISK ASSESSMENT FOR CPP-603 ENGINEERING EVALUATION COST ANALYSIS (EE/CA) EDF-4489 01
17-JUN-04 PETERSON, D. T. CPP-603 ENGINEERING EVALUATION COST ANALYSIS (EE/CA) ALTERNATIVES RRH-11-04 00
16-JUN-04 BRAGASSA, J. L. REMOVAL ACTION WORK PLAN FOR THE DECONTAMINATION AND DECOMMISSIONING (D&D) OF BUILDING CPP-627, THE REMOTE ANALYTICAL FACILITY DOE/NE-ID-11158 00
16-JUN-04 BRAGASSA, J. L. CPP-627 CERCLA REMOVAL ACTION WASTE MANAGEMENT PLAN (WMP) DOE/NE-ID-11171 00
14-JUN-04 AR COORDINATOR CPP-627 REMOVAL ACTION - IDAHO COMPLETION PROJECT (ICP) ADMINISTRATIVE RECORD (AR) INDEX FOR NON TIME CRITICAL REMOVAL ACTION (NTCRA) AT IDAHO NATIONAL ENGINEERING & ENVIRONMENTAL LABORATORY (INEEL) SP-6 CPP-627 DECONTAMINATION AND DECOMMISSION (D&D) AR.INDEX.NTCRA.CPP-627 00
10-JUN-04 TOMLINSON, G. E. DOSE ESTIMATES FOR INTEC-603 BASIN ACTIVITIES 24881 00
04-JUN-04 RASCH, D. N. SLUDGE REMOVAL FROM THE CPP-603 BASINS TS-ETSD-04-113 00
01-JUN-04 PROVENCHER, R. B. ACTION MEMORANDUM FOR THE DECONTAMINATION AND DECOMMISSIONING (D&D) OF BUILDING CPP-627, THE REMOTE ANALYTICAL FACILITY DOE/NE-ID-11164 00
19-APR-04 DOE NOTICE OF AVAILABILITY - DEPARTMENT OF ENERGY (DOE) PROPOSES DEMOLITION OF REMOTE ANALYTICAL FACILITY BUILDING (CPP-627) AT IDAHO NATIONAL ENGINEERING AND ENVIRONMENTAL LABORATORY (INEEL) 24839 00
15-APR-04 BRAGASSA, J. L. ENGINEERING EVALUATION COST ANALYSIS (EE/CA) FOR THE DECONTAMINATION AND DECOMMISSIONING (D&D) OF BUILDING CPP-627, THE REMOTE ANALYTICAL FACILITY DOE/NE-ID-11157 01
08-APR-04 ROSENBERGER, M. S. VICINITY DISCHARGES ELIMINATION WORK PLAN FOR THE HAZARDOUS WASTE MANAGEMENT ACT (HWMA) AND THE RESOURCE CONSERVATION RECOVERY ACT (RCRA) POST CLOSURE PERMIT FOR INTEC WASTE CALCINING FACILITY (WCF) AT THE INEEL DOE/NE-ID-11138 00
31-MAR-04 HOLMES, F. C. APPROVAL TO PROCEED WITH PREPARATION OF ENGINEERING EVALUATION & COST ANALYSIS (EE/CA) FOR DECOMMISSION AND DISMANTLEMENT (D&D) OF CPP-627, IDAHO NUCLEAR TECHNOLOGY AND ENGINEERING CENTER (INTEC) INEEL 24838 00
23-MAR-04 THOMPSON, R. G. QUALITY ASSURANCE PROJECT PLAN (QAPJP) FOR WAG-1 WAG-2 WAG-3 WAG-4 WAG-5 WAG-6 WAG-7 WAG-10 AND DEACTIVATION, DECONTAMINATION, AND DECOMMISSIONING (D&D&D) - APPENDIX C TO MONITORING SYSTEM AND INSTALLATION PLAN - DOE/ID-10774, REVISION 3 (REV.03) DOE/ID-10587 08
10-MAR-04 WINSTON, P. L. ENGINEERING DESIGN FILE (EDF) - CPP-603 RADIONUCLIDE SAMPLE RESULTS EDF-4235 01
09-MAR-04 MCCARTHY, J. M. ENGINEERING DESIGN FILE (EDF) - STREAMLINED RISK ASSESSMENT FOR CPP-603 ENGINEERING EVALUATION COST ANALYSIS (EE/CA) EDF-4488 00
09-MAR-04 MCCARTHY, J. M. ENGINEERING DESIGN FILE (EDF) - SOIL CONTAMINATION GROUNDWATER PATHWAY RISK ASSESSMENT FOR CPP-603 ENGINEERING EVALUATION COST ANALYSIS (EE/CA) EDF-4489 00
16-FEB-04 DOORNBOS, M. H. WHITE PAPER - BUILDING CPP-627 DEACTIVATION, DECONTAMINATION AND DECOMMISSIONING (D&D&D) CAN BE PERFORMED UNDER THE DEPARTMENT OF ENERGY'S (DOE) CERCLA REMOVAL ACTION AUTHORITY 24828 00
16-FEB-04 DOORNBOS, M. H. APPROVAL NEEDED OF CERCLA TIME CRITICAL REMOVAL ACTION (TCRA) FOR DEACTIVATION, DECONTAMINATION AND DECOMMISSIONING (D&D&D) OF BUILDING CPP-627 AND TRANSMITTAL OF WHITE PAPER JHV-019-04 00
27-JAN-04 ARROWOOD, J. R. DOSE ESTIMATES FOR INTEC-603 BASIN ACTIVITIES 24837 00
19-DEC-03 HOLMES, F. C. DOE MEMORANDUM - APPROVAL TO PROCEED WITH PREPARATION OF AN ENGINEERING EVALUATION COST ANALYSIS (EE/CA) FOR FUEL STORAGE BASIN COMPLEX AT CPP-603, IDAHO NUCLEAR TECHNOLOGY AND ENGINEERING CENTER (INTEC), INEEL 24818 00
19-DEC-03 HOLMES, F. C. ENGINEERING EVALUATION COST ANALYSIS (EE/CA) FOR DEACTIVATION OF CPP-603 FUEL STORAGE BASINS EM-ER-03-318 00
09-DEC-03 WINSTON, P. L. ENGINEERING DESIGN FILE (EDF) - CPP-603 RADIONUCLIDE SAMPLE RESULTS EDF-4235 00
09-DEC-03 VAN AUSDEIN, L. A. ENGINEERING DESIGN FILE (EDF) - QUANTIFICATION OF THREE DEBRIS OBJECTS FROM THE SOUTH BASIN OF CPP-603 USING THE UNDERWATER GAMMA SPECTROMETER SYSTEM (TUGS) EDF-4271 00
20-AUG-03 VAN AUSDEIN, L. A. ENGINEERING DESIGN FILE (EDF) - CPP-603 BASINS - FISSILE MATERIAL IN PARTICULATE FORM BASED ON 137CS TO 235U RATIO EDF-3535 00
15-MAY-03 MCCARTHY, J. M. ENGINEERING DESIGN FILE (EDF) - ACCEPTABLE RESIDUAL INVENTORY CALCULATIONS FOR CPP-603 EDF-3684 00
12-SEP-02 THOMPSON, R. G. QUALITY ASSURANCE PROJECT PLAN (QAPJP) FOR WAG-1 WAG-2 WAG-3 WAG-4 WAG-5 WAG-6 WAG-7 WAG-10 AND INACTIVE SITES - ALSO APPENDIX C TO DOE/ID-10774, REV.02 DOE/ID-10587 07
01-JUN-01 DOE DRAFT ENVIRONMENTAL ASSESSMENT (EA) - DEACTIVATION, DECOMMISSIONING, AND DISMANTLEMENT (D&D&D) OF CPP-603 BASIN PROJECT DOE/EA-1368 00
09-MAY-01 PYLE, J. D. ENGINEERING DESIGN FILE (EDF) - POTENTIAL AIR EMISSIONS ASSOCIATED WITH DEACTIVATION, DECOMMISSIONING AND DISMANTLEMENT (D&D&D) OF CPP-603A BASIN PROJECT EDF-1931 00
08-MAY-01 MCCARTHY, J. M. ENGINEERING DESIGN FILE (EDF) - D&D OF CPP-603 BASIN PROJECT - GROUNDWATER MONITORING - TRANSPORT SIMULATION APPROACH FOR THE RISK ASSESSMENT FOR DEACTIVATION OF IDAHO NUCLEAR TECHNOLOGY AND ENGINEERING CENTER (INTEC) PLANT BUILDING CPP-603 EDF-1962 00
20-SEP-00 THOMPSON, R. G. QUALITY ASSURANCE PROJECT PLAN (QAPJP) FOR WAG-1 WAG-2 WAG-3 WAG-4 WAG-5 WAG-6 WAG-7 WAG-10 & INACTIVE SITES (APPENDIX J TO MONITORING SYSTEM AND INSTALLATION PLAN (MSIP) OU 3-13 GROUP 5 DOE/ID-10782, REV.01, APPENDIX C TO DOE/ID-10774, REV.00 & REV DOE/ID-10587 06
01-APR-00 INEEL COMMUNITY RELATIONS INEEL REPORTER - AGENCIES TO DECIDE FATE OF THE CALCINER - APRIL 2000 - MAY 2000 (04/2000 - 05/2000) 21216 00
01-DEC-99 INEEL COMMUNITY RELATIONS INEEL REPORTER - NOVEMBER 1999 AND DECEMBER 1999 (11/99 & 12/99) - INEEL INSERTS PROBE TUBE INTO BURIED WASTE PIT 10964 00
01-JUN-99 WAGNER, E. P. PROCESS DESCRIPTION AND OPERATING HISTORY FOR CPP-601, CPP-604 AND CPP-627 FUEL REPROCESSING COMPLEX AT INEEL INEEL/EXT-99-00400 00
01-NOV-98 INEEL COMMUNITY RELATIONS INEEL REPORTER - AGENCIES ISSUE REVISED CLEANUP PLAN FOR TEST AREA NORTH (TAN) - NOVEMBER 1998 (11/98) & DECEMBER 1998 (12/98) 17370 00
21-SEP-98 CHAMBERS, R. MULTI-AGENCY RADIATION SURVEY & SITE INVESTIGATION MANUAL (MARSSIM) INVESTIGATION FOR CPP-709 RADIONUCLIDES RC-10-98 00
08-JUL-98 DOE PRELIMINARY DRAFT - ENVIRONMENTAL ASSESSMENT (EA) AND DEACTIVATION PLAN FOR OBSOLETE SPENT NUCLEAR FUEL (SNF) PROCESSING, STORAGE, AND SUPPORT FACILITIES AT IDAHO NUCLEAR TECHNOLOGY AND ENGINEERING CENTER (INTEC) DOE/EA-1244 00
29-APR-98 JENKINS, T. W. RESPONSE TO RECOMMENDATION ON PROPOSED SOILS REPOSITORY AT INEEL OPE-ER-73-98 00
01-DEC-97 BAUMER, A. R. QUALITY ASSURANCE PROJECT PLAN (QAPJP) FOR WAG-1, WAG-2, WAG-3, WAG-4, WAG-5, WAG-6, WAG-7 & WAG-10 & INACTIVE SITES (FORMERLY INEL-95/0086) DOE/ID-10587 05
01-NOV-97 INEEL COMMUNITY RELATIONS INEEL REPORTER - NOVEMBER 1997 & DECEMBER 1997 (11/97 & 12/97) - CITIZENS ASK FOR INPUT ON FOUR COMPREHENSIVE INVESTIGATIONS, PIPELINE FOR TRANSURANIC (TRU) WASTE, TECHNOLOGY ON ACID PIT & NOTICE OF INTENT (NOI) FOR ENVIRONMENTAL IMPACT STATEMENT (EI 14284 00
01-AUG-97 JONES, R. W. FIELD SAMPLING PLAN (FSP) FOR D&D OF CPP-631 RALA BUILDING & CPP-709 & CPP-734 MONITORING STATIONS AT ICPP INEEL/EXT-97-00805 00
08-JUL-97 FALCONER, K. L. LISTING CODES APPLICABLE TO DISPOSITION OF INVESTIGATION DERIVED WASTE (IDW) ORIGINATING FROM IDAHO CHEMICAL PROCESSING PLANT (ICPP) KLF-150-97 00
01-JUN-97 JONES, R. K. LIMITED SCOPE & HAZARD CHARACTERIZATION PLAN FOR SOIL DISTURBANCE CERCLA RADIOLOGICAL CHARACTERIZATION AT IDAHO CHEMICAL PROCESSING PLANT (ICPP) - CPP-701 PETROLEUM CONTAMINATED SOIL INEEL/EXT-97-00677 00
01-JUN-97 LABUY, S. A. HEALTH & SAFETY PLAN (HSP) FOR D&D OF CPP-631, CPP-709 & CPP-734 INEL-95/0292 01
23-DEC-96 JENSEN, N. R. TRANSMITTAL OF THREE TECHNICAL MEMORANDA ON TECHNOLOGY SCREENING REMEDIAL ACTION (RA) OBJECTIVES AND APPLICABLE OR RELEVANT AND APPROPRIATE REQUIREMENTS (ARARS) OPE-ER-199-96 00
19-JUN-95 GREEN, L. A. TRANSMITTAL OF DRAFT WASTE AREA GROUP 3 (WAG-3) SCREENING LEVEL ECOLOGICAL RISK ASSESSMENT (SLERA) OPE-ER-117-95 00
01-JUN-95 LABUY, S. A. HEALTH & SAFETY PLAN (HSP) FOR DECONTAMINATION AND DECOMMISSIONING (D&D) OF CPP-631, CPP-709 & CPP-734 INEL-95/0292 00
23-MAR-95 GREEN, L. A. TRANSMITTAL OF VALIDATED DATA FOR PERCHED WATER SAMPLING, DECEMBER 1994 (12/94) AND JANUARY 1995 (01/95) OPE-ER-052-95 00
01-MAR-95 BAUMER, A. R. QUALITY ASSURANCE PROJECT PLAN (QAPJP) FOR WAG-1, WAG-2, WAG-3, WAG-4, WAG-5, WAG-6, WAG-7 & WAG-10 - EFFECTIVE 12/97 DOCUMENT ID NUMBER IS DOE/ID-10587, REV.05 INEL-95/0086 04
09-JAN-95 RENO, S. L. IDAHO DEPARTMENT OF HEALTH AND WELFARE DEPARTMENT OF ENVIRONMENTAL QUALITY (IDHW-DEQ) INFORMAL COMMENTS ON DRAFT WASTE AREA GROUP 3 (WAG-3) SATURATED ZONE CONCEPTUAL MODEL 15044 00
22-NOV-94 RENO, S. L. IDAHO DEPARTMENT OF HEALTH AND WELFARE DEPARTMENT OF ENVIRONMENTAL QUALITY (IDHW-DEQ) COMMENTS ON TECHNICAL MEMORANDUM ON THE HYDROGEOLOGY AT THE IDAHO CHEMICAL PROCESSING PLANT (ICPP) OPERABLE UNIT (OU) 3-13 15040 00
28-OCT-94 JENKINS, T. W. TRANSMITTAL OF DRAFT TECHNICAL MEMORANDUM ON THE HYDROGEOLOGY AT THE IDAHO CHEMICAL PROCESSING PLANT (ICPP) 17286 00
14-OCT-94 INEL COMMUNITY RELATIONS COMMUNITY RELATIONS PLAN KICKOFF FACT SHEET - CITIZENS INVITED TO GIVE EARLY INPUT 8028 00
30-AUG-94 RENO, S. L. IDAHO DEPARTMENT OF HEALTH AND WELFARE DEPARTMENT OF ENVIRONMENTAL QUALITY (IDHW-DEQ) INFORMAL COMMENTS ON SEDIMENT LAYERING EFFECT ON CONTAMINANT TRANSPORT FOR NONPERCHED UNSATURATED AREAS AT THE IDAHO CHEMICAL PROCESSING PLANT (ICPP) 5779 00
30-AUG-94 RENO, S. L. IDHW-DEQ INFORMAL COMMENTS ON TECHNICAL MEMORANDUM ASSESSMENT PORFLOW BOUNDARY CONDITIONS FOR USE IN THE IDAHO CHEMICAL PROCESSING PLANT (ICPP) UNSATURATED ZONE MODEL & ATTACHMENT A CYLINDRICAL COORDINATE OPTION PORFLOW 5784 00
10-AUG-94 MEYER, L. ENVIRONMENTAL PROTECTION AGENCY (EPA) COMMENTS ON DRAFT AQUIFER CHARACTERISTICS TECHNICAL MEMORANDUM 5778 00
15-JUL-94 BURNS, S. M. IDAHO DEPARTMENT OF HEALTH & WELFARE (IDHW) REQUEST FOR IDAHO CHEMICAL PROCESSING PLANT (ICPP) STACK EMISSIONS DATA SMB-05-94 00
01-MAY-94 DOE COMPREHENSIVE WELL SURVEY FOR INEL VOLUME II (VOL.02), REVISION 3 (REV.03) - EXPERIMENTAL BREEDER REACTOR (EBR) & IDAHO CHEMICAL PROCESSING PLANT (ICPP) DOE/ID-10402,VOL.02 03
01-APR-94 BUGGER, B. DOE NEWS - ENGINEERS NEW SENSOR SYSTEM WITH ARMS CONTROL, CLEANUP APPLICATIONS 7595 00
30-MAR-94 BUGGER, B. DOE NEWS - RETECH SIGN AGREEMENT FOR TEST MELT OF CONTAMINATED METAL 7559 00
28-FEB-94 WINCO BACKGROUND CONCENTRATIONS OF SELECTED METALS & RADIONUCLIDES IN BIG LOST RIVER ALLUVIUM AT ICPP, REVISION 1 (REV.01) 14143 00
01-FEB-94 WENZEL, D. R. RADIOLOGICAL SAFETY ANALYSIS COMPUTER PROGRAM (RSAC-5) USER'S MANUAL WINCO-1123 01
15-OCT-93 BUGGER, B. DOE NEWS - WINCO PRIVATE VENDOR DEMONSTRATES TECHNOLOGY FOR CLEANER DECONTAMINATION 6836 00
05-AUG-93 COE, M. DOE NEWS - IDAHO CHEMICAL PROCESSING PLANT (ICPP) TRANSITION PLAN MADE AVAILABLE 6710 00
04-AUG-93 HUESTIS, G. M. SOIL TREATABILITY STUDY (TS) OF INEL SOILS INCLUDING ICPP SOILS GMH-01-93 00
02-AUG-93 BARRY, G. A. TRANSMITTAL OF DRAFT SAMPLING & ANALYSIS PLAN (SAP) FOR WASTE AREA GROUP 3 (WAG-3) THROUGH WASTE AREA GROUP 10 (WAG-10) 93MSE/ID-225 00
01-AUG-93 BARRY, G. A. SAMPLING & ANALYSIS PLAN (SAP) FOR THE WASTE AREA GROUP 3 (WAG-3) THROUGH WASTE AREA GROUP 10 (WAG-10) RADIONUCLIDE CONTAMINATED SOILS TREATABILITY STUDY (TS) 6744 00
24-JUN-93 COE, M. DOE NEWS - DOE COMPLETES ENVIRONMENTAL ASSESSMENT (EA) ON UPGRADING CHEMICAL PLANT TANK FARM 6548 00
01-JUN-93 BUGGER, B. DOE NEWS - WINCO COORDINATES EFFORT TO RECYLE CONTAMINATED METAL 6520 00
01-JUN-93 SEHLKE, G. WELL FITNESS EVALUATION FOR INEL, VOLUME 1 (VOL.01) DOE/ID-10392,VOL.01 00
01-JUN-93 SEHLKE, G. WELL FITNESS EVALUATION FOR INEL, VOLUME 2 (VOL.02) - ICPP DOE/ID-10392,VOL.02 00
01-JUN-93 SEHLKE, G. WELL FITNESS EVALUATION FOR INEL, VOLUME 3 (VOL.03) - ICPP CONT'D & INEL MIDDLE, NORTH & SOUTH DOE/ID-10392,VOL.03 00
08-JAN-93 RHODES, D. W. EVALUATION OF RECORDS FOR WASTE GENERATED AT ICPP & DISPOSED AT RWMC DURING THE PERIOD OF 1960 - 1983 DWR-01-93 00
14-JAN-92 JONES, K. L. STATE OF IDAHO, REQUEST FOR INFORMATION KXJ-9-92 00
06-NOV-91 EVANS, T. A. TANK CLOSURE NOTIFICATION - THIRTY (30) DAY NOTICE OF CLOSURE FORM FOR TANK NUMBERS: CFA 713-4, 713-5, 731, 732, 741-7, IRC-1, 01SSW 103, 01SSW 111, 01SSW 104, NRF 503, 511, TAN 783, 792, 707, CPP-SAA 152 & 153 SGS-464-91 00
13-OCT-91 EARLE, O. K. HIGH LEVEL WASTE TANK FARM REPLACEMENT (HLWTFR) PROJECT USING DEVICES TO LOCATE UNDERGROUND UTILITIES 6589 00
10-SEP-91 EVANS, T. A. TANK CLOSURE NOTIFICATION - THIRTY (30) DAY NOTICE OF CLOSURE FORM FOR TANK NUMBER: CHEMICAL PROCESSING PLANT (CPP) VES-YDA-106 SGS-353-91 00
22-AUG-91 EVANS, T. A. TANK CLOSURE NOTIFICATION - THIRTY (30) DAY NOTICE OF CLOSURE FORM FOR TANK NUMBER: CHEMICAL PROCESSING PLANT (CPP) VES-HBF-102 SGS-334-91 00
31-JUL-91 EVANS, T. A. TANK CLOSURE NOTIFICATION - THIRTY (30) DAY NOTICE OF CLOSURE FORM FOR TANK NUMBERS: CHEMICAL PROCESSING PLANT (CPP) VES-UTI-653, VES-UTI-655 & VES-UTI-654 SGS-289-91 00
25-APR-91 BERGEMAN, N. L. INFORMATION REQUEST FOR WELLS IN VICINITY OF TEST REACTOR AREA (TRA), TEST AREA NORTH (TAN) & IDAHO CHEMICAL PROCESSING PLANT (ICPP) SGS-127-91 00
04-JAN-91 NOT SPECIFIED IDAHO CHEMICAL PROCESSING PLANT (ICPP) WASTE AREA GROUP (WAG) ASSESSMENT 6625 00
26-APR-90 GREEN, L. A. RESPONSE TO STATE QUESTIONS 6635 00
08-NOV-89 SEHLKE, G. RESPONSE TO EPA'S NOTICE OF DEFICIENCY FOR WINCO'S ACCELERATED CLOSURE PLAN (CP) SCHEDULE GS-15-89 00
01-NOV-88 THOMAS, T. R. MODELING HYPOTHETICAL GROUNDWATER TRANSPORT OF NITRATES, CHROMIUM, & CADMIUM AT IDAHO CHEMICAL PROCESSING PLANT (ICPP) WINCO-1060 00
27-JUL-87 HUNTER, B. R. FINAL REPORT FOR 2ND (SECOND) PECR - LOG NO. 87072729 6629 00
24-OCT-86 LEE, J. L. UNUSUAL OCCURRENCE REPORT (UOR) WL-212 CONTAMINATED LIQUID SPILL WIN-86-0032-CPP 00
22-OCT-86 LEE, J. L. UNUSUAL OCCURRENCE REPORT (UOR) INADVERTENT TRANSFER RESULTING IN LOSS OF WASTE SOLUTION WIN-86-0034-CPP 00
02-FEB-86 NEBEKER, R. L. SOURCES OF INFORMATION FOR CERCLA STUDY NEB-3-86 00
15-JAN-86 WALLACE, M. T. HAZARDOUS WASTE STREAMS AT CPP 7756 00
09-AUG-85 SMITH, D. L. SUMMARY OF RALA D&D STATUS DLS-31-85 00
01-JUL-85 MOSER, C. L. RALA OFF GAS CELL AND STORAGE TANK (CPP-631 & VES-702) DECONTAMINATION AND DECOMMISSIONING (D&D) PLAN WINCO-1032 00
11-APR-85 NISHIMOTO, D. D. IDENTIFICATION OF RADIOACTIVE MIXED WASTE STREAMS AT THE IDAHO CHEMICAL PROCESSING PLANT (ICPP) DDN-01-85 00
26-OCT-84 MESERVEY, R. H. TRANSMITTAL OF CHEMICAL PROCESSING PLANT 601 (CPP-601) PROCESS CELLS A, B, C, D, & L - D&D FINAL REPORT RHM-33-84 00
19-JUL-84 IKENBERRY, T. A. RADIOLOGICAL CONTROLS FOR THE DECONTAMINATION OF LOW LEVEL WASTE (LLW) PROJECT EQUIPMENT TAI-05-84 00
28-NOV-83 HICKS, F. E. DISPOSITION OF STOCKPILED LOW LEVEL CONTAMINATED SOIL EXCAVATED DURING THE LOW LEVEL WASTE (LLW) PROJECT PHASE I AT THE IDAHO CHEMICAL PROCESSING PLANT (ICPP) - M-K PROJECT S-2258, ICWA 83-49 MK-83-E-1792 00
01-MAY-83 SCHMIDT, D. A. INTERNAL TECHNICAL REPORT - RADIOLOGICAL CHARACTERIZATION & DECISION ANALYSIS FOR CHEMICAL PROCESSING PLANT 603 (CPP-603) BIF FILTER ROOM WM-F1-83-006 00
01-MAY-81 BRADFORD, D. J. INTERNAL TECHNICAL REPORT - CHARACTERIZATION OF THE RALA OFF GAS CELL, CHEMICAL PROCESSING PLANT 631 (CPP-631) WM-F1-81-010 00
01-MAR-81 BRADFORD, D. J. INTERNAL TECHNICAL REPORT - CHEMICAL PROCESSING PLANT 633 (CPP-633) NAK FURNACE CHARACTERIZATION WM-F1-81-004 00
01-APR-73 NICCUM, M. R. FLOODING POTENTIAL AT THE IDAHO CHEMICAL PROCESSING PLANT (ICPP) 4962 00
01-JUN-72 PAIGE, B. E. BURIED WASTE (BW) LINE REGISTER NATIONAL REACTOR TESTING STATION (NRTS) PART IV CPP ACI-110 00


Send Questions and Comments to: RecordsManagement@icp.doe.gov

Previous Page | Administrative Record Home Page